LBJ Express Project Schedule & Timeline

What Changes Can you Expect in 2012?

 

I-35E/Stemmons Freeway - Loop 12 to Forest Lane

  • Drill shaft work will continue between Manana Road and Crown.
  • Bridge work at the intersection of I-35E and Northwest Highway.
  • Substructures of bridges between Manana Road and Crown.
  • Drill shaft work between Northwest Highway and Manana Road.
  • Frontage Road work between Manana Road and Crown.
  • Temporary construction detours will be put in place at the Loop 12/I-35E intersection.

I-35E/Stemmons Freeway and I-635/LBJ Freeway Interchange

  • Drainage work on the I-635 Eastbound Frontage Road between I-35E and Josey Lane.

I-635/LBJ Freeway – Luna Road to Welch Road

  • Complete Noise Wall construction along residential areas.
  • Complete the reconstruction of the Joe Ratcliff, Marsh Lane, and Rosser Road bridge.
  • Begin frontage road reconstruction.

I-635/LBJ Freeway and Dallas North Tollway Interchange

  • Welch Road demolition (January) and reconstruction. 
  • Noise Wall construction along residential areas eastbound between Welch Road and DNT.
  • Utility relocation along the westbound Frontage Road from Montfort Drive to DNT and DNT to Welch Road.

I-635/LBJ Freeway – Montfort Drive to US-75/Central Expressway

  • Utility relocation scheduled to complete.
  • Complete reconstruction of Montfort Drive bridge and the Hillcrest Road overpass.
  • Begin Preston Road reconstruction (late 2012)
  • Begin frontage road reconstruction.
 
 
CLICK HERE to view the PDF File
Check out the TxDOT LBJ Express Project Tracker by clicking here.
 
 